Several roads in Grundy County will be repaired this summer.

The Grundy County Board last week approved a resolution for the work. Here is Highway Engineer Eric Gibson.

The bid for the cape seal portion went to AC Pavement in the amount of $1.04 million; seal coat bid went to Steffens 3-D for $726,000; D. Construction was the lowest bidder for the hot-mix asphalt portion for $925,000; Denler was the lowest bidder for cracking filling at $74,000 and the pavement striping portion of the project went to Precision Pavement in the amount of $127,000.

Gibson also said the board approved another project.

Both projects will begin this summer.